GUIDELINES  FOR  IMPLEMENTING  COAL  RESEARCH  PROJECTS


15.0 EXTENSION OF PROJECT DURATION


All projects which have incurred slippage of one year or more or likely to incur such slippage should immediately be brought to the notice of the Sub-Committee of SSRC along with corrective actions proposed to be taken up by the implementing agency to minimise the slippage and views of the nodal agency at its next meeting. 

Sanctioned duration of the project may be extended only in exceptional cases. Request for extension should be sent using proforma (Form VII),nine months prior to the date of expiry of the project in 15 copies, through the Head of the Institution.